Huawei MA5800 Stand-Alone Commissioning

After the hardware installation, a stand-alone MA5800 should be commissioned to ensure that the stand-alone Huawei OLT MA5800 works in the normal state. The following recommended commissioning tasks and sequences are for reference only. Different offices have different conditions; therefore, it is recommended that customers, with the assistance of our engineers, modify commissioning tasks according to actual requirements.

Powering On the Device
This topic describes how to power on the device to ensure that all the boards can be normally powered on.

Prerequisites
The after-installation check and the power-on check must be performed on the device.

Procedure
There are two kinds of devices: the indoor device and the outdoor device.
− Powering on the indoor device
1. Connect the input power supply of the DC PDU.
2. Turn on the output control switch of the DC PDU.
− Powering on the outdoor device
1. Connect the input power supply of the AC PDU.
2. Turn on the output control switch of the AC PDU.
3. Turn on the output control switch of the power system.
4. Turn on the output control switch of the DC PDU.

Result
The device can be normally powered on, and the STATUS indicator on the fan tray is on for 1s and off for 1s repeatedly, and so is the RUN ALM indicator on the board.

Commissioning the Power Supply System
This topic describes how to commission the power supply to ensure the reliable and stable power supply provided for the device.

Prerequisites
Only Huawei MA5800 supports this operation.
The two independent power supplies of the DC power distribution unit (PDU) supply power to the cabinet concurrently.
Procedure
Step 1 Disconnect the first power supply, and check the power supply of the cabinet.
Step 2 Restore the first power supply to power the cabinet.
Step 3 Disconnect the second power supply, and check the power supply of the cabinet.
Step 4 Restore the second power supply to power the cabinet

Procedure
Step 1 Turn off the switch on the PDU that corresponds to one power board, and check the power supply for the service board.
Step 2 Turn on the switch again.
Step 3 Repeat steps 1 and 2 to check the other power board.